Batch Size

You are currently browsing articles tagged Batch Size.

Continuous Delivery reduces defect probability and cost

Continuous Delivery often challenges conventional wisdom within the IT industry, and by advocating the rapid release of value-add to reduce risk it contradicts the traditional belief that a low release cadence is an effective risk reduction strategy. How can releasing software more frequently reduce both defect probability and defect cost?

The probability of a defect is the likelihood of a change within a changeset unexpectedly impeding value-add and imposing an opportunity cost. Given the defect probability of a changeset is proportional to its size we can calculate the defect probability of a change as follows:

Fix More With Less - Defect Probability

n = number of changesets
probability = (1 / 2n) * 100 [percentage]

The above formula indicates that decreasing changeset size by increasing the number of changesets will reduce defect probability, and this is confirmed by Don Reinertsen’s assertion that “many smaller experiments produce less variation than one big one“. For example, if a change is released in 1 changeset there is a 1 in 2 chance or 50% probability of failure. If it was instead released in 3 changesets there would be a 1 in 8 chance or 12.5% probability of failure.

The cost of a defect is the product of cost per unit time and duration, where cost per unit time represents economic impact and duration represents lifetime.

cost = cost per unit time [currency] * duration [unit time]

A defect has an inception date at its outset, a discovery date when diagnosed, and a resolution date when fixed. The interactions between these dates and cost per unit time enable a division of defect cost into sunk cost and opportunity cost. The sunk cost of a defect represents the economic damage already incurred at the point of discovery, while opportunity cost represents the economic damage still to be incurred.

Fix More With Less - Defect Cost

sunk cost duration = discovery date – inception date [unit time]
sunk cost = cost per unit time * sunk cost duration [currency]

opportunity cost duration = resolution date – discovery date [unit time]
opportunity cost = cost per unit time * opportunity cost duration [currency]

cost = sunk cost + opportunity cost [currency]

As cost per unit time is controlled by market conditions it is far easier to reduce opportunity cost duration by shortening lead times. This can be accomplished via batch size reduction, as Mary and Tom Poppendieck have observed that “time through the system is directly proportional to the amount of work-in-process” due to Little’s Law:

lead time = work in progress [units] / completion rate [units per time period]

Little’s Law is universal for all stable systems in which these variables are consistent long-term averages, and it is mathematical proof that reducing batch size will reduce lead time. For example, if a jug contains 4 litres of water and pours 2 litres per second then it will empty in 2 seconds. If instead the jug contained 2 litres of water and still poured 2 litres per second it would empty in 1 second.

Releasing smaller changesets more frequently into production can also reduce sunk cost duration, as small batches accelerate feedback. A smaller batch size will decrease the lead time and complexity associated with each changeset, creating faster feedback loops that will reduce the time required to discover a defect.

Consider an organisation with an average changeset size of 24 changes and an average lead time of 12 days. How can we reduce the defect probability of the next production release R1?

Fix More With Less - Defect Probability Smaller Changeset

n = 1
probability = (1 / 21) * 100 = 50%

Based on the binomial probabilities involved we recommend to the organisation that it reduce defect probability by applying batch size reduction to R1 and splitting its changeset into 2 smaller releases R1 and R2. This would decrease defect probability from 50% to 25%.

Fix More With Less - Defect Probability Larger Changeset

n = 2
probability = (1 / 22) * 100 = 25%

Unfortunately the organisation ignores our advice to release smaller changesets, and the release of R1 at a later date introduces a defect D1 that remains undiscovered for 6 days. D1 impedes a sufficient amount of value-add that a cost per unit time of £20,000 per day is estimated, which means a sunk cost of £120,000 has already been incurred and an opportunity cost of £240,000 is forecast. The organisation immediately triages D1 for a fix, but how can we reduce its opportunity cost?

Fix More With Less - Defect Cost Large

cost per unit time = £20,000
sunk cost = 6 days * £20,000 = £120,000
opportunity cost = 12 days * £20,000 = £240,000
overall cost = sunk cost + opportunity cost = £360,000

Given the organisation currently has an average batch size of 24 changes per changeset and a 12 day average lead time, Little’s Law computes an average completion rate of 2 changes per day and informs us that a reduced batch size of 12 changes per changeset would produce a 6 day lead time.

completion rate = work in process / lead time
completion rate = 24 changes per changeset / 12 days = 2 changes per day

lead time = work in process / completion rate
lead time = 12 changes per changeset / 2 changes per day = 6 days

Based on Little’s Law we again recommend to the organisation a halved batch size of 12 changes per changeset, and this time our advice is accepted. A fix for D1 is included in the next changeset released into production in 6 days, which produces an opportunity cost saving of £120,000.

Fix More With Less - Defect Cost Smaller Opportunity Cost

cost per unit time = £20,000
sunk cost = 6 days * £20,000 = £120,000
opportunity cost = 6 days * £20,000 = £120,000
overall cost = sunk cost + opportunity cost = £240,000

As well as decreasing the total cost of D1 by 33%, the new lead time of 6 days increases the rate of feedback for future production defects. When a subsequent release introduces defect D2 at a lower cost per unit time of £10,000 per day the reduced size and complexity of the offending changeset means D2 is discovered in only 3 days.

Fix More With Less - Defect Cost Smaller Sunk Cost

cost per unit time = £10,000
sunk cost = 3 days * £10,000 = £30,000
opportunity cost = 6 days * £10,000 = £60,000
overall cost = sunk cost + opportunity cost = £90,000

When we triage D2 we discover its cost per unit time has decreased to £1,000 per day, meaning its sunk cost is a poor indicator of opportunity cost and its Cost of Delay is lower than expected. Based upon the new 6 day lead time we recommend to the organisation that it defer a D2 fix for at least one release in order to implement pending value-add of greater value than the £12,000 opportunity cost of D2.

Fix More With Less - Defect Cost Even Smaller Opportunity Cost

cost per unit time = 3 days * £10,000, 12 days * £1,000
sunk cost = 3 days * £10,000 = £30,000
opportunity cost = 12 days * £1,000 = £12,000
overall cost = sunk cost + opportunity cost = £42,000

The assumption within many IT organisations that risk is directly proportional to rate of change is flawed, as it assumes a constant large batch size. Risk is actually proportional to size of change, and a low release cadence of large changesets is not as effective a risk reduction strategy as a high release cadence of small changesets. Continuous Delivery enables the release of smaller changesets to rapidly release value-add as well as reducing both the probability and cost of defects.

Tags: , , , ,

No Projects

Projects kill flow and teams. Focus on products, not projects

Since the Dawn of Computer Time, enormous sums of money and embarrassing amounts of time have been squandered upon software projects that have delivered little or no return on investment, with projects floundering between segregated Business and IT divisions squabbling over overestimated value-add and underestimated delivery dates. Given Grant Rule’s assertion that “studies too numerous to mention show that software projects are challenged or fail“, why are software projects so prone to failure and why do they persist?

To answer these questions, we must understand what constitutes a software project and why its delivery model is incongruent with product development. If we start with the PRINCE 2 project definition of “a temporary organization that is needed to produce a unique and predefined outcome or result at a pre-specified time using predetermined resources“, we can offer a concise definition as follows:

A project is a fixed amount of time and money assigned to deliver value-add

The key characteristic of a software project appears to be its fixed end date, which as a delivery model has been repeatedly debunked by IT practitioners such as Allan Kelly denouncing “endless, pointless discussions about when it will be done… successful software doesn’t have a pre-specified end date” and Marc Lankhorst arguing that “over 80% of IT spending in large organisations is on maintenance“. However, the fixed end date of a software project is invariably a consequence of its requirement for a collection of value-adding features to be simultaneously delivered, suggesting an augmented definition of:

A project is a fixed amount of time and money assigned to deliver a large batch of value-add

Once we view software projects as large batches of value-add, we can apply The Principles Of Product Development Flow by Don Reinertsen and better understand why so many projects fail:

  1. Increased cycle time – a project might not be deliverable on a particular date unless either demand is throttled or capacity is increased, e.g. artifically reduce user demand or increase staffing levels
  2. Increased variability – a project might be delayed due to unpredictable blockages in the value stream, e.g. testing of features B and C blocked while testing of feature A takes longer than expected
  3. Increased feedback delays – a project might incur significant costs due to slow feedback on bad design decisions and/or defects increasing rework, e.g. failures in feature C not detected until features A and B have passed testing
  4. Increased risk – a project might have an increased probability and cost of failure due to increased requirements/technology change, increased variation, and increased feedback delays
  5. Increased overheads  – a project might endure development inefficiencies due to increased requirements/technology change, e.g. feature C development time increased by need to understand complexity of features A and B
  6. Increased inefficiencies – a project might encounter increased transaction costs due to increased requirements/technology change e.g. feature A slow to release as features B and C also required for release
  7. Increased irresponsibility – a project might suffer from diluted responsibilities, e.g. staff member has responsibility for delivery of feature A but is unincentivised to participate in delivery of features B or C

Don also provides a compelling explanation as to why the project delivery model remains prevalent, by explaining how large batches can become institutionalised as they “appear to have scale economies that increase efficiency [and] appear to reduce variability“. Software projects might indeed appear to be efficient due to perceived value stream inefficiencies and the counter-intuitiveness of batch size reduction, but from a product development standpoint it is an inefficient, ineffective delivery model that impedes value, quality, and flow.

There is a compelling alternative to the project delivery model – product development flow, in which we apply economic theory to Lean product development practices in order to flow product designs through our organisation. Product development flow emphasises the benefits of batch size reduction and encourages a one piece continuous flow delivery model, in order to reduce costs and improve return on investment.

Discarding the project delivery model in favour of product development flow requires an entirely different mindset, as epitomised by Grant urging us to “accommodate the ideas of flow production and lean systems thinking” and Allan affirming that “BAU isn’t a dirty word… enhancing products is Business As Usual, we should be proud of that“. On that basis the No Projects movement was conceived by Joshua Arnold to promote the valuation of products over projects, and anointed as:

Projects kill flow and teams. Focus on products, not projects

Tags: , , , ,

Continuous Delivery enables batch size reduction

Continuous Delivery aims to overcome the large delivery costs traditionally associated with releasing software, and in The Principles of Product Development Flow Don Reinertsen describes delivery cost as a function of transaction cost and holding cost. While transaction costs are incurred by releasing a product increment, holding costs are incurred by not releasing a product increment and are proportional to batch size – the quantity of in flight value-adding features, and the unit of work within a value stream.

Economic Batch Size [Reinertsen]

The above graph shows that a reduction in transaction cost alone will not dramatically impact delivery cost without a corresponding reduction in batch size, and this mirrors our assertion that automation alone cannot improve cycle time. However, Don also states that “the primary controllable factor that enables small batches is low transaction cost per batch“, and by implementing Continuous Delivery we can minimise transaction costs and subsequently release smaller change sets more frequently, obtaining the following benefits:

  1. Improved cycle time – smaller change sets reduce queued work (e.g. pending deployments), and due to Little’s Law cycle time is decreased without constraining demand (e.g. fewer deployments) or increasing capacity (e.g. more deployment staff)
  2. Improved flow – smaller change sets reduce the probability of unpredictable, costly value stream blockages (e.g. multiple deployments awaiting signoff)
  3. Improved feedback – smaller change sets shrink customer feedback loops, enabling product development to be guided by Validated Learning (e.g. measure revenue impact of new user interface)
  4. Improved risk – smaller change sets reduce the quantity of modified code in each release, decreasing both defect probability (i.e. less code to misbehave) and defect cost (i.e. less complex code to debug and fix)
  5. Improved overheads – smaller change sets reduce transaction costs by encouraging optimisations, with more frequent releases necessitating faster tooling (e.g. multi-core processors for Continuous Integration) and streamlined processes (e.g. enterprise-grade test automation)
  6. Improved efficiency – smaller change sets reduce waste by narrowing defect feedback loops, and decreasing the probability of defective code harming value-adding features (e.g. user interface change dependent upon defective API call)
  7. Improved ownership – smaller change sets reduce the diluted sense of responsibility in large releases, increasing emotional investment by limiting change owners (e.g. single developer responsible for change set, feedback in days not weeks)

Despite the business-facing value proposition of Continuous Delivery, there may be no incentive from the business team to increase release cadence. However, the benefits of releasing smaller change sets more frequently – improved feedback, risk, overheards, efficiency, and ownership – are also operationally advantageous, and this should be viewed as an opportunity to educate those unaware of the power of batch size reduction. Such a scenario is similar to the growth of Continuous Integration a decade ago, when the operational benefits of frequently integrating smaller code changes overcame the lack of business incentive to increase the rate of source code integration.

Business requirements = minimum release cadence
Operational requirements = maximum release cadence

A persistent problem with increasing release cadence is Eric Ries’ assertion that “the benefits of small batches are counter-intuitive“, and in organisations long accustomed to a high delivery cost it seems only natural to artificially constrain demand or increase capacity to smooth the value stream. For example, our organisation has a 28 day cycle time of which 7 days are earmarked for release testing. In this situation, decreasing cadence to a 36 day cycle time appears less costly than increasing cadence to a 14 day cycle time, as release testing will ostensibly decrease to 19% of our cycle time rather than increase to 50%. However, this ignores both the holding cost of constraining demand and the long-unimplemented optimisations we would be compelled to introduce to achieve a lower release cadence (e.g. increased level of test automation).

Improving cycle time is not just about using Continuous Delivery to reduce transaction costs – we must also be courageous, and release more with less.